King Street-Old Town Metrorail Station Access Improvement Project Update: Lot Closes Nov. 18

Major construction of the King St. Metro, including relocation of bus bays, is slated to begin November 18
Major work on the King Street-Old Town Metrorail Station Access Improvement Project has been moved to mid-November. Preliminary construction including the construction of interim bus bays began in August. The major construction activities initially scheduled to start on Sept. 9, including the closure of the bus loop and Kiss & Ride and initiating bus service to the relocated bus bays, are now slated to begin on November 18. Customers using bus service at the King Street-Old Town Metrorail Station are encouraged to check the project web page for the most up-to-date information.
While the project will bring many benefits to transit users, there will be significant construction impacts through fall 2020.
Safety and access upgrades will include improved pedestrian access and safety; three additional bus bays; improved traffic flow; new designated areas for bikes, shuttles, Kiss & Ride, and carshare vehicles; and improved landscaping, lighting, and aesthetics.
The project will occur in two phases. During the first phase, which will last approximately 18 months, bus bays will be relocated to surrounding streets. Other facilities – including locations for Kiss & Ride, car share and shuttles – will remain closed for the duration of project construction. During the second phase (approximately 6 months), the new bus bays will be completed and open, but the Kiss & Ride, car share and shuttle area will remain closed.
Phase 1 Construction Impacts – Fall 2018 – Winter 2020 ( SUBJECT TO CHANGE)
During construction, please expect the following:
  • There will be no Kiss & Ride area during construction. All customers who use these areas should use either Eisenhower Avenue or Braddock Road Metrorail stations (Phases 1 and 2).
  • The existing parking lot and bus loading area will be under construction, except for pedestrian paths to the bus bays (Phase 1).
  • Bus bays will be temporarily relocated to Diagonal Road, Daingerfield Road, Cameron Street and King Street. Wayfinding signs will direct bus riders to their temporary bay (Phase 1). The bus bays will be moved back to the station after Phase 1 is completed.
  • Pedestrians using the Carlyle pedestrian tunnel will be required to cross Diagonal Road after exiting the pedestrian tunnel east of Duke Street, and then again at the mid-block crossing to enter the Metro station (Phase 1).
  • A temporary pedestrian path will run from the main entrance of the station to the mid-block crosswalk and the bus waiting area at Diagonal Road through the construction area. An additional pedestrian path will be parallel to the train tracks, near the station, between the main entrance and King Street (Phases 1 and 2).
  • The Trolley drop-off area and Metro Access Van and taxi pick-up and drop-off area will be temporarily relocated to the north side of Cameron Street just east of the north entrance to the King Street-Old Town Metrorail station entrance at Commonwealth Avenue. Taxis may also continue to use the zone in front of the Embassy Suites Hotel, or Alexandria Union Station (Phases 1 and 2).
  • There will be no shuttle area within the station, and all local shuttle service must use either Eisenhower Avenue or Braddock Road Metrorail stations (Phases 1 and 2).
  • Bicycle parking will continue to be provided at the station, and the Capital Bikeshare stations on Diagonal Road and Commonwealth Avenue will remain open throughout the duration of the project (Phases 1 and 2).
  • Drivers should be aware of increased congestion and limited street parking during project construction. Station users should plan for additional time getting to and from Metro. (Phases 1 and 2).
The City provides information on alternate ways of getting around, including walking, biking, and teleworking, through the transportation resource program GO Alex.
The King St. Metro station when construction is complete.
The Access Improvement Project will not impact train service or cause any station closures. A separate WMATA project to rehabilitate the station platform will affect train service in summer 2019. The City is working with WMATA to coordinate both projects.
The Access Improvement Project was approved by City Council in 2012 after several years of study, community input, design, and review by City boards and commissions. Over the past five years, the City has worked closely with WMATA and these stakeholders to finalize the design process.
To learn more about the project and what to expect during construction, visit the King Street-Old Town Metro Access Improvement Project web page.