Five Tracks Narrow to Three in Alexandria. Here’s Why Virginia Is Adding a Fourth.

Five tracks funnel into three just west of Union Station. A six-mile rail project aims to give passenger trains a clearer path north.

A year after the groundbreaking, crews have installed a new railroad signal structure at Slaters Lane. Here’s what the work means for riders at Alexandria Union Station.

Fourth Track
Fourth Track

ALEXANDRIA, VA — November 24, 2026 — If you’ve ever boarded an Amtrak train at Alexandria Union Station or taken Virginia Railway Express (VRE) into Washington, you’ve traveled on a railroad that also carries freight. Just west of the station, five tracks feeding in from the Manassas and Fredericksburg lines narrow to three. When several trains need the same stretch of track, somebody has to wait.

On an average day in fiscal 2025, passengers got on or off an Amtrak train in Alexandria more than 1,000 times. Amtrak’s Virginia figures count only passengers who boarded or stepped off here. VRE commuters and passengers who stayed aboard as their trains passed through add to the traffic on those tracks.

Virginia’s answer is the Alexandria Fourth Track. The Virginia Passenger Rail Authority is adding a fourth track alongside the existing three for six miles from Alexandria into Arlington. That gives dispatchers room to route passenger trains and freight trains separately on the approach to Washington. Amtrak and VRE still serve Alexandria while the work is underway.

If this is the first you’re hearing of it, the project broke ground at Union Station a year ago. What brought it back into the news this week is progress at Slaters Lane. According to an update shared with The Zebra on Monday, crews installed a structure for railroad signals and worked on a crossover, the connection that lets a train move from one track to another.

Where the fourth track will go

The $238.4 million project follows the railroad from just west of Union Station to the southern end of the Long Bridge project in Arlington, near the Long Bridge Aquatics & Fitness Center. Crews will shift existing tracks to make room. In July 2025, Alexandria City Council voted unanimously to authorize temporary access to city land for construction, including portions of the station property.

The authority’s before-and-after photo slider shows where that extra track would fit. Drag the divider across the image to compare the existing railroad with the proposed layout.

Fourth Track 2
Fourth Track 2

What crews have finished so far

Near Crystal City, crews finished installing steel retaining walls where the railway and the land beside it sit at different heights. The walls hold the soil in place and give the railroad room to expand. “Completing the walls clears the way for CSX to install new signal equipment and track,” the update said.

Utility work began in spring 2025, and rail construction started in January 2026. The design also leaves room for VRE’s planned platform improvements at Alexandria and Crystal City.

Can you still catch a train in Alexandria?

Yes. Amtrak continues to serve Alexandria Union Station on Callahan Drive. Some VRE trains now begin or end in Alexandria because of Long Bridge construction. Riders on those trains traveling between Alexandria and Washington need to transfer.

For Thanksgiving week, VRE will suspend service systemwide on Thursday and Friday, November 26 and 27, and resume Monday, November 30. Looking ahead, VRE announced on November 20 that its January 4, 2027, schedule changes will temporarily cut three round trips during construction along the wider rail corridor. The cuts include the last peak-period trip in each direction on both the Manassas and Fredericksburg lines, plus two Manassas trains that run against the usual rush-hour flow.

In April, The Zebra reported on the planned May 1–4 King Street closure near Union Station between Russell and Daingerfield roads. In that part of the corridor, the railroad bridges over King Street and Commonwealth Avenue are part of a separate bridge replacement project along the same corridor. The adjacent Metro bridges are outside the scope of that work.

Mary Wadland

Mary Wadland is the Publisher and Editor in Chief of The Zebra Press, the award-winning Alexandria news publication she founded in 2010 with a mission of celebrating community, culture, and all the good news happening across the city. A longtime community advocate and storyteller, Mary was selected for the Alexandria Chamber of Commerce inaugural 40 Under 40 class, served on numerous boards, been awarded the 2024 Business Philanthropist of the Year Award by Volunteer Alexandria, and has served as president of Living Legends of Alexandria Board since the fall of 2021. Known for her deep local roots, sharp editorial instincts, and passion for connecting people through journalism, she has spent decades chronicling the personalities, businesses, events, and civic life that make Alexandria unique. Originally from Delray Beach, Florida, Mary is a Phi Beta Kappa history-major graduate of Hollins College in Roanoke, Virginia, and has been part of Alexandria’s publishing and media community since 1987.

Related Articles

0 0 votes
Article Rating
Subscribe
Notify of
guest

This site uses Akismet to reduce spam. Learn how your comment data is processed.

0 Comments
Oldest
Newest Most Voted
Back to top button
0
Would love your thoughts, please comment.x
()
x